Water

EVALUATION, DESIGN, AND CONSTRUCTION

WATER SYSTEM REHABILITATION

ROUNDUP, MT

Planning

  • 2009 CIP
  • 2009 PER
  • 2010 Grant Applications
  • 2010 CIP Update
  • 2011 PER Update
  • 2012 CIP Update
  • 2012 Grant Applications
  • 2013 PER Update
  • 2014 CIP Update
  • 2014 Grant Applications

Phase 1

  • 6,000 LF Water Main
  • Well Pump and Well House Upgrades
  • By-Pass Existing Infiltration Gallery
  • New Service Lines to Curb Stops
  • Completed In 2013

Phase 2

  • 5,600 LF Water Main
  • Abandonment of 5 Blocks of Old Main
  • New Water Meters
  • New Service Lines to Curb Stops
  • 2 Block of Full Street Restoration
  • Completed in 2015

Phase 3

  • 7,200 LF Of New Water Main
  • Increase Fire Flow to New School
  • Transmission Main Replacement